CASES

Project information

  • Category: Microgrid Project
  • Region & Country: Switzerland, Europe
  • Client: Integrator
  • Project Configuration: 375kW/771.67kWh BESS+EMS+ECC4P+42kWpSolar System+EV Charger
  • Project Time: 2026
  • Applied Solution: Commercial & Industrial Solutions
  • Applied EMS: EMS Controller Set
  • Applied BESS: EGS257
  • Applied Service: Engineering
  • Applied Logics: Peak Shaving, Grid Power Exchange Control, Load Shifting, Black Start